The Lisburn/Lurgan Ballast Rehabilitation Project (see last issue) continued during the period under review, the six-week project between Lisburn and Moira running from February 14 to March 25.
The used ballast, which was removed using the hired-in 13-wagon Irish Rail spoil train, has been unloaded by an excavator at a site adjacent to the closed station at Ballinderry on the Lisburn to Antrim branch.
This branch features significant adverse gradients from the junction at Lisburn for around five miles, which has caused difficulties with adhesion.
Enjoy more Rail Express Magazine reading every month.
Click here to subscribe & save.
The problem has been rectified by treating, as required, the railhead in the affected area with water sprayed by NIR’s Geismar-built waterjetter, which is based at Belfast Fortwilliam Traincare depot.
On March 22-23, the nocturnal positioning movements carried out prior to the start of the ballast cleaning/topping-up operation were observed.
The empty spoil train was hauled from Ballinderry to Lisburn by GM No. 8111.
A NIR tamper then ran wrong road (on the down line) from Lisburn Yard to the work site near Moira, and was followed shortly after by IR ballast cleaner No. 781.
Read more in the May issue of RE – on sale now!